Abstrak: Jembatan wisata carocok ini merupakan pembangunan infrastruktur atau salah satu
proyek yang tidak hanya menawarkan daya tarik wisata yang unik tetapi juga mencerminkan
kemajuan teknologi dan estetika arsitektur, tujuan dari perencanaan review desain jembatan wisata
carocok painan yaitu menghasilkan detail engineering design (DED), meningkatkan standar
keselamatan pengunjung dan mengoptimalkan anggaran pembangunan infrastruktur jembatan.
Perencanaan teknik jembatan ini dibagi dalam beberapa tahapan kegiatan yaitu pengumpulan data
lapangan dan perencanaan penggambaran, survey pendahuluan yang dilakukan survey topografi,
survey geometric dan survey hidrologi lalu melakukan pengumpulan data teknis serta pedoman
teknis. hasil survey hidrologi yang telah dilaksanakan dan di analisa dan mengingat rencana
jembatan terletak pada daerah muara sungai maka perlu dipasang pengaman Batu Krib untuk
mengamankan ABT, perencanaan review ded jembatan wisata carocok painan direkomendasikan
jenis jembatan: beton prategang I girder, bentang jembatan: 40,60 M Klas C, komponen utama
memakai beton mutu fc’=45Mpa, diaphragma memakai beton mutu fc’=35Mpa, lantai kendaraan
dari beton bertulang fc’= 30 Mpa, Abutment fc’= 25 Mpa, pondasi digunakan pondasi tiang
pancang Mutu Baja Ø < 12 fy = 240 Mpa (U24) (Polos) Ø > 12 fy = 390 Mpa (U39) (Ulir).
Kata kunci: Pembangunan Jembatan, DED (detail engineering design), wisata, beton prategang I
girder.
Abstract: This carocok tourist bridge is an infrastructure development or one of the projects that
not only offers a unique tourist attraction but also reflects technological advances and architectural
aesthetics, the purpose of planning the design review of the carocok painan tourist bridge is to
produce a detailed engineering design (DED), improve visitor safety standards and optimise the
bridge infrastructure development budget.
The engineering planning of this bridge is divided into several stages of activities, namely field data
collection and drawing planning, preliminary surveys carried out topographic surveys, geometric
surveys and hydrological surveys and then collecting technical data and technical guidelines. the
results of the hydrological survey that have been carried out and analysed and considering that the
bridge plan is located in the estuary area, it is necessary to install Krib Stone safety to secure ABT,
the planning of the ded review of the carocok painan tourist bridge is recommended bridge type:
prestressed concrete I girder, span: 40.60 M Klas C, the main component uses concrete quality
fc‘=45Mpa, the diaphragm uses concrete quality fc’=35Mpa, the vehicle floor is reinforced
concrete fc‘=30 Mpa, Abutment fc’=25 Mpa, the foundation is used pile foundation Quality Steel Ø
< 12 fy = 240 Mpa (U24) (Plain) Ø > 12 fy = 390 Mpa (U39) (Threaded).
Keywords: Bridge construction, DED (detail engineering design), tourism, pre-stressed